Buildings

Building Construction in 2014

Construction is underway for the Building D Addition and Renovation and the New Engineering and Technology Center in the former Buildings G and H.

Other building projects focus on refreshing and maintenance work. For detailed information about work on a specific building, click on the building name on the left.

Campus-Wide Projects

Building Entrance Repairs: 6/25/2014 – 9/30/2014 UPDATED
Replacement and repairs to exterior entrances. Alternate entrances will be marked.

  • Building L: Door L3, 7/8/2014 – 8/4/2014
  • Building L: Door L4: 7/21/2014 – 7/30/2014
  • Building W: Door W1, 7/17/2014 – 7/25/2014
  • Building W: Door W2, 8/8/2014 – 8/15/2014
  • Building W: Door W3, 8/25/2015 - 9/30/2014

See Map PDF for locations.

Hand Dryer Installation, Ongoing
Select restrooms around campus will be closed for brief periods of time while we continue replacing paper towel dispensers with hand dryers. Hand dryers reduce our reliance on paper products and the associated costs as well as the amount of material being sent to landfills.