Campus Construction

Buildings

Building B: Boiler Upgrades 9/12/16 - 4/28/17  
Contractor will continue commissioning of new equipment.

Building C: Building Automation System, Mechanical Rooms, 11/21/16-4/28/17   
Equipment is in place. Integration is in progress. Slight fluctuations in temperature may occur.

Building E: Building Automation System, Mechanical Rooms, 12/21/16-4/28/17   
Equipment is in place. Integration is in progress. Slight fluctuations in temperature may occur.

Building F: August 2016 - Fall 2018
Construction is in progress.  See Map.

HPC:  Bathrooms 125 and 126, 3/18/17 - 3/26/17
Washrooms will be remodeled to become ADA compliant.

Building M: 3/6/17-8/15/18   
Building M construction fencing is installed. See Map   De
molition to start in April.

Buildings L: Building Automation System 4/3/17-4/28/17     
HVAC valves and controls are being upgraded in the HVAC rooms to improve heating and cooling control.  The following schedule identifies the areas that will be affected.  Facilities will be providing temporary HVAC when needed.

Schedule:

  • 4/3/17: Areas affected – restrooms L122, L124, corridor L199U, classrooms L126, L126c, L126J Office L126B, L126M, L130, storage rooms L126A, L126G, L126H, L126L, L130B electrical room L126K.
  • 4/4/17: Areas affected – corridor L199U, L199W, classroom 109D, storage L127, office L133, IT closet L137.
  • 4/24/17: Areas affected – classroom 109

Systems will be manually regulated after each of these dates and should be fully operational by the end of May.  Slight fluctuations in temperature may occur throughout and April and May.

Building P: Chiller Plant Upgrade November 2016 - March 2017     
Expansion is underway to add two new chillers.   See Map

Building P: Building Automation System 3/13/17-9/18/17     
HVAC valves and controls are being upgraded throughout the building to improve heating and cooling control.  Systems will be manually regulated and should be fully operational by the end of April.  Slight fluctuations in temperature may occur throughout March and April.

Building S: Building Automation System, Mechanical Rooms, 8/16-4/28/17   
Equipment is in place.  Integration is in progress. Slight fluctuations in temperature may occur.

Building X:  Nursing Area Remodel, Sept. 2016 - Mar. 2017
The construction is now complete. Equipment is being installed.

Building X:  Physical Therapy Assistant Lab, 3/6/17 - 6/30/17
Classrooms X236A and X236B are closed and will be renovated into a lab space for the Physical Therapy Assistant program.

Building Y:  Classroom Y203b, 3/18/17 - 3/26/17
Classroom will be reconfigured.

Building Z:  3rd Floor, 3/6/17 - 4/1/17
Lighting system installation will be taking place during this time.

Main Campus

Campus Wide Fire Alarm Testing - 1/30/17 - 3/30/17 
The horns and strobes will be tested in the early morning from 6:00am to 8:00 am, with a proceeding announcement "This is only a test and evacuation is not required." Evacuation of the building IS required for any fire alarm activation outside of 6:00am to 8:00 am, unless there is an announcement that the activation was due to the testing.  Fire alarm testing in elevator hoistways will take place on Thursday, Feb. 23 and Friday, Feb. 24. This will require individual elevators to be down for a short time during the testing.
For questions, please contact Sara Gibson x6923 sgibson@harpercollege.edu

Window Washing - 3/27/17 - 5/5/17 
Contractor will be working on cleaning exterior windows.