Campus Construction

Buildings

Building B: Boiler Upgrades 9/12/16 - 5/30/17  
Contractor will continue commissioning of new equipment.

Building C: Building Automation System, Mechanical Rooms, 11/21/16-5/30/17   
Equipment is in place. Integration is in progress. Slight fluctuations in temperature may occur.

Building D: Meeting Room D139  5/1/17 - 8/15/17  
Meeting room D139 will be offline for interior and exterior repairs.

Building E: Building Automation System, Mechanical Rooms, 12/21/16-5/30/17   
Equipment is in place. Integration is in progress. Slight fluctuations in temperature may occur.

Building F: August 2016 - Fall 2018
Construction is in progress.  See Map.

Building M: 3/6/17-8/15/18   
Construction is in progress. See Map.

Buildings L: Building Automation System 4/3/17-7/31/17     
HVAC valves and controls are being upgraded in the HVAC rooms to improve heating and cooling control.  The following schedule identifies the areas that will be affected.  Facilities will be providing temporary HVAC when needed.

Schedule:

  • Saturday, 5/27/17: Second floor classrooms L200, L202, L204, Bookstore L260 thro L260L  - HVAC will be affected throughout the day. Temperature fluctuations may occur.  Facilities will have spot coolers available if needed.
  • 4/24/17 thought 7/31/17: Entire Building – HVAC will be operating with manual controls, slight temperature fluctuations may occur. Contact facilities and temperatures will be manually adjusted as needed.

     

Building P: Chiller Plant Upgrade November 2016 - 5/30/17     
Expansion is substantially complete. Contractor is working on punchlist items. See Map

Building P: Building Automation System 3/13/17-9/18/17     
HVAC valves and controls are being upgraded throughout the building to improve heating and cooling control.  Systems will be manually regulated and should be fully operational by the end of April.  Slight fluctuations in temperature may occur.

Building S: Building Automation System, Mechanical Rooms, 8/16-5/30/17   
Equipment is in place.  Integration is in progress. Slight fluctuations in temperature may occur. 

Building W: Roof Work, Friday, 5/26/17
Roof patching will occur on the south east 2nd floor roof. Staff may notice fumes or hear noise while this is taking place.

Building X:  Physical Therapy Assistant Lab, 3/6/17 - 6/30/17
Classrooms X236A and X236B. Construction is complete. Equipment will be ordered.

Building Z:  3rd Floor, 3/6/17 - 5/31/17
Lighting system installation will be taking place during this time.

Main Campus

Algonquin Road Entrance:  5/22/17- 5/23/17
Buildings A & M circle driveway will be partially closed on Monday and Tuesday for water main work.  A two way traffic path will be created on the east side of the circle to allow access to Building A drop off area.  Harper police will assist with traffic flow.
  See Map